The federal Government of Nigeria on Sunday provided details of N162.50 billion Sukuk Funds Released for the of 44 road projects in the country, across the Six Geo-Political Zones in Nigeria. According to the government, the aim behind the release of the information is to offer insight for public accountability.
This breakdown was provided in series of tweets by the Senior Special Assistant To President Muhammdu Buhari on Public Affairs, Ajuri Ngelale via his official twitter account. The details as provided by Ajuri is given below;
Zonal Breakdown:
- North-Central: N26.5bn (2020) 143.44 kms (2020) 8 Roads
- North-East: N30.5bn 277.53 kms 8 Roads,
- North-West: N26.5bn 227.47 kms 7 Roads,
- South-West: N27bn 59.74 kms 6 Roads
- South-East: N26bn 99.45 kms 5 Roads
- South-South: N26bn 121.78 kms 10 Roads
NORTH-CENTRAL BREAKDOWN: EIGHT ROADS
- DUALIZATION OF SULEJA-MINNA ROAD PHASE II (KM 40+000 – 101+000) IN NIGER STATE – Contractor: Salini Nigeria Ltd; Contract Sum: N36.2bn; Current Completion Level: 17.20%; 2020 SUKUK Payment: N2.5bn; Road/Bridge Works; Kms Covered (2020): 14km
- ABUJA-ABAJI ROAD (SECTION 1: INTERNATIONAL AIRPORT LINK ROAD JCT – SHEDA VILLAGE JCT) – Contractor: Dantata & Sawoe; Contract Sum: N28.6bn; Current Completion Level: 96.11%; 2020 SUKUK Payment: N1.0bn; PROJECT COMPLETION; Kms Covered (2020): 2.2km
- ABUJA-LOKOJA ROAD: SECTION IV (KOTON KARFE – LOKOJA); Contractor: Gitto Construction – Contract Sum: N31.08bn; Current Completion Level: 76.0%; 2020 SUKUK Payment: N2.5bn; Asphalt Wearing and 1st & 2nd Coat surface dressing on shoulders with lined drains; Kms Covered (2020): 5.5km
- DUALIZATION OF OBAJANA JUNCTION TO BENIN PHASE 2: SECTION 1 (OBAJANA JUNCTION TO OKENE) – Contractor: CGC Nigeria Ltd; Contract Sum: N30.56bn; Current Completion Level: 32.66%; 2020 SUKUK Payment: N3.5bn; Ongoing Dualization works; Kms Covered (2020): 63.05km
- CONSTRUCTION OF OJU/LOKO-OWETO BRIDGE TO LINK BENUE & NASARAWA WITH NEW APPROACH ROADS – Contractor: RCC Nigeria Ltd; Contract Sum: N51.61bn; Current Completion Level: 96.7%; 2020 SUKUK Payment: N6.0bn; PROJECT COMPLETION; Kms Covered (2020): 5.0km
- RECONSTRUCTION OF BIDA-LAPAI-LAMBATA ROAD IN NIGER STATE – Contractor: CGC Nigeria Ltd; Contract Sum: N33.3bn; Current Completion Level: 13.06%; 2020 SUKUK Payment: N5.0bn; CH25+000 – CH35+500, CH43+600 – CH55+000 up to A/C Wearing Course; Kms Covered (2020): 20.9km
- RECONSTRUCTION OF MAKURDI-NAKA-ADOKA-ANKPA ROAD IN BENUE STATE – Contractor: Gilmor Engineering; Contract Sum: N27bn; Current Completion Level: 0.53%; 2020 SUKUK Payment: N3.0bn; CH70+500 – CH58 (12.5Km), CH70+650 – CH150 (12.5Km) up to A/C Binder Course; Kms Covered (2020): 25.0km
- CONSTRUCTION OF ROAD LINKING BARO PORT TO GULU TOWN IN NIGER STATE – Contractor: GR Building Nigeria; Contract Sum: N10.61bn; Current Completion Level: 0.00%; 2020 SUKUK Payment: N3.0bn; PROJECT COMMENCEMENT; Kms Covered (2020): 7.75km
NORTH-EAST BREAKDOWN: EIGHT ROADS
- KANO-MAIDUGURI ROAD: (SECTION II – SHUARI LINK TO AZARE) – Contractor: Setraco Nigeria Ltd; Contract Sum: N65.31bn; Current Completion Level: 86.62%; 2020 SUKUK Payment: N11.0bn; Ongoing Construction; Kms Covered (2020): 53.93km
- KANO-MAIDUGURI ROAD: (SECTION III – AZARE LINK TO POTISKUM) – Contractor: Mothercat Ltd; Contract Sum: N45.18bn; Current Completion Level: 91.79%; 2020 SUKUK Payment: N2.0bn; PROJECT COMPLETION; Kms Covered (2020): 0km – Toll Plazas/Weighbridges
- KANO-MAIDUGURI ROAD: (SECTION IV – POTISKUM LINK TO DAMATURU) – Contractor: CGC Nigeria Ltd; Contract Sum: N51.90bn; Current Completion Level: 80.51%; 2020 SUKUK Payment: N4.0bn; Main Carriageway Works; Kms Covered (2020): 94.0km
- KANO-MAIDUGURI ROAD: (SECTION V – DAMATURU LINK TO MAIDUGURI) – Contractor: CCECC Nigeria Ltd; Contract Sum: N67.79bn; Current Completion Level: 50.94%; 2020 SUKUK Payment: N4.0bn; Main Carriageway Works; Kms Covered (2020): 59.6km
- REHABILITATION OF GWOZA-DAMBOA-GONIRI-NGAMDU IN BORNO STATE – Contractor: Hajaig Construction Nigeria Ltd; Contract Sum: N34.60bn; Current Completion Level: 0.00%; 2020 SUKUK Payment: N3.0bn; Site Clearing/Earthworks, Culverts, Pavement & Surfacing; Kms Covered (2020): 15.0km
- RECONSTRUCTION OF MAYO BELWA-JADA-GANYE-TOUGO ROAD IN ADAMAWA STATE – Contractor: Triacta Nigeria Ltd; Contract Sum: N22.69bn; Current Completion Level: 14.14%; 2020 SUKUK Payment: N3.0bn; Asphalt Wearing & Reconstruction; Kms Covered (2020): 42.0km
- CONSTRUCTION OF IBI BRIDGE IN TARABA STATE – Contractor: RCC Nigeria Ltd; Contract Sum: N57.07bn; Current Completion Level: 0.00%; 2020 SUKUK Payment: N2.0bn; Piles and Pile caps for Axis 2 & 3, 4 & 5 Ibi Side; Kms Covered (2020): Bridgeworks
- REHABILITATION OF NGURU-GASHUA-BAYAMARI ROAD: SECTION II (GASHUA-BAYAMARI) IN YOBE STATE – Contractor: Ric Roc Construction Ltd; Contract Sum: N11.77bn; Current Completion Level: 0.14%; 2020 SUKUK Payment: N1.5bn; Rehabilitation up to Asphalt Binder Kms Covered (2020): 13.0km
NORTH-WEST BREAKDOWN: SEVEN ROADS
- KANO-MAIDUGURI ROAD: (SECTION I – KANO LINK TO WUDIL WITH LINK TO SHUARI) – Contractor: Dantata & Sawoe; Contract Sum: N55.1bn; Current Completion Level: 67.51% ;2020 SUKUK Payment: N4.5bn; Interchange 1,2 & Carriageway; Kms Covered (2020): 58.0km
- DUALIZATION OF KANO-KATSINA ROAD: (PHASE 1 – KANO TOWN AT DAWANAU ROUNDABOUT TO KATSINA STATE BORDER) IN KANO STATE – Contractor: CCECC Nigeria Ltd; Contract Sum: N14.0bn; Current Completion Level: 51.48%; 2020 SUKUK Payment: N2.75bn; Ongoing Dualization; Kms Covered (2020): 57.0km
- CONSTRUCTION OF KADUNA EASTERN BY-PASS – Contractor: Eksiogulari Nigeria Ltd; Contract Sum: N38.19bn; Current Completion Level: 39.40%; 2020 SUKUK Payment: N4.0bn; CH16+000 – CH37+000 (Road Works up to A/C Binder Course), Bridgeworks at Chikaji CH35; Kms Covered (2020): 21.0km
- CONSTRUCTION OF KANO WESTERN BY-PASS – Contractor: Dantata & Sawoe; Contract Sum: N22.77bn; Current Completion Level: 66.98%; 2020 SUKUK Payment: N4.0bn; Asphalt Wearing; Bridgework (3 & 4); CH 0+425 – CH 9+030 Median Drain & Slope Protection (Bridge 2); Kms Covered (2020): 12.47km
- DUALIZATION OF KANO-KATSINA ROAD: (PHASE II – KANO/KATSINA BORDER LINK TO KATSINA STEEL ROLLING MILLS ROUNDABOUT) – Contractor: CCECC Nigeria Ltd; Contract Sum: N29.65bn; Current Completion Level: 0.00%; 2020 SUKUK Payment: N3.75bn; Ongoing Dualization; Kms Covered (2020): 26.5km
- REHABILITATION OF SOKOTO-TAMBUWAL-JEGA-KONTAGORA-MAKERA ROAD: (SECTION I – SOKOTO / KEBBI STATES) – Contractor: Triacta Nigeria Ltd; Contract Sum: N30.45bn; Current Completion Level: 68.52%; 2020 SUKUK Payment: N5.0bn; Carriageway Reconstruction; Kms Covered (2020): 40.0km
- REHABILITATION OF AJINGI-JAHUN-KAFIN HAUSA ROAD IN JIGAWA STATE -Contractor: H & M Nigeria Ltd; Contract Sum: N25.03bn; Current Completion Level: 0.00%; 2020 SUKUK Payment: N2.5bn; Carriageway Reconstruction; Kms Covered (2020): 12.5km
Read also; Covid-19 – 32 African Countries get over $19 billion Loan from IMF
SOUTH-EAST BREAKDOWN: FIVE ROADS
- ENUGU-PH DUAL CARRIAGEWAY: (LOKPANTA-UMUAHIA) – Contractor: Setraco Nigeria; Contract Sum: N39.54bn; Current Completion Level: 64%; 2020 SUKUK Payment: N5.0bn; Kms Covered (2020): 21.7km
- RECONSTRUCTION OF ENUGU-PORT HARCOURT DUAL CARRIAGEWAY: (SECTION II – UMUAHIA TO ABA) – Contractor: Arab Contractors Ltd; Contract Sum: N50.89bn; Current Completion Level: 36.21%; 2020 SUKUK Payment: N5.5bn; Carriageway Construction; Kms Covered (2020): 25.75km
- RECONSTRUCTION OF ENUGU-PORT HARCOURT ROAD: (SECTION III – ENUGU TO LOKPANTA) – Contractor: CGC Nigeria Ltd; Contract Sum: N32.31bn; Current Completion Level: 28.77%; 2020 SUKUK Payment: N5.0bn; Carriageway Construction; Kms Covered (2020): 27.0km
- RECONSTRUCTION OF ONITSHA-ENUGU EXPRESSWAY: (SECTION I – AMANSEA TO ENUGU STATE BORDER) – Contractor: RCC Nigeria Ltd; Contract Sum: N62.06bn; Current Completion Level: 29.92%; 2020 SUKUK Payment: N6.5bn; Carriageway Reconstruction; Kms Covered (2020): 12.0km
- RECONSTRUCTION OF OLD ENUGU-ONITSHA ROAD: (OPI JUNCTION-UKEHE OKPATU-ABOH UDI-OJI TO ANAMBRA BORDER) – Contractor: Arab Contractors; Contract Sum: N31.94bn; Current Completion Level: 4.75%; 2020 SUKUK Payment: N4.0bn; Carriageway Reconstruction; Kms Covered (2020): 13.0km
SOUTH-WEST BREAKDOWN: SIX ROADS
- RECONSTRUCTION OF BENIN-OFOSU-ORE-AJEBANDELE-SHAGAMU EXPRESSWAY – Contractor: RCC Nigeria Ltd; Contract Sum: N65.22bn; Current Completion Level: 82.96%; 2020 SUKUK Payment: N4.5bn; Carriageway Reconstruction; Kms Covered (2020): 15.0km
- PAVEMENT STRENGTHENING AND ASPHALT OVERLAY OF AJEBANDELE-IJEBU ODE-SHAGAMU ROAD IN OGUN STATE – Contractor: RCC Nigeria Ltd Contract Sum: N71.64bn; Current Completion Level: 26.50%; 2020 SUKUK Payment: N4.5bn; Asphalt Overlay & Pavement Reinforcement; Kms Covered (2020): 13.0km
- DUALIZATION OF IBADAN-ILORIN EXPRESSWAY: (SECTION II – OYO-OGBOMOSO ROAD IN OYO STATE) – Contractor: RCC Nigeria Ltd; Contract Sum: N47.50bn; Current Completion Level: 73.35%; 2020 SUKUK Payment: N5.0bn; Ongoing Dualization; Piling; Pile Caps; Kms Covered (2020): 8.0km
- REHABILITATION AND EXPANSION OF LAGOS-BADAGRY EXPRESSWAY: (SECTION I – AGBARA JUNCTION TO BENIN BORDER) – Contractor: CGC Nigeria Ltd; Contract Sum: N63.02bn; Current Completion Level: 9.30%; 2020 SUKUK Payment: N4.5bn; Ongoing Expansion works; Kms Covered (2020): 8.70km
- REHABILITATION OF THE OUTER MARINA ROAD IN LAGOS STATE – Contractor: CCECC Nigeria Ltd; Contract Sum: N9.27bn; Current Completion Level: 0.00%; 2020 SUKUK Payment: N4.0bn; Reconstruction works; Kms Covered (2020): 4.54km
- DUALIZATION OF LAGOS-OTTA ROAD – Contractor: Julius Berger; Contract Sum: N56.70bn; Current Completion Level: 15.38%; 2020 SUKUK Payment: N4.557bn Carriageway Reconstruction; Kms Covered (2020): 10.50km
SOUTH-SOUTH BREAKDOWN: TEN ROADS
- DUALIZATION OF OBAJANA JUNCTION TO BENIN: (SECTION II – OKENE TO AUCHI) – Contractor: Mothercat Ltd; Contract Sum: N21.29bn; Current Completion Level: 48.85%; 2020 SUKUK Payment: N4.0bn Carriageway & Bridgeworks; Kms Covered (2020): 56.87km
- DUALIZATION OF OBAJANA JUNCTION TO BENIN: (SECTION III – AUCHI TO EHOR) – Contractor: Dantata & Sawoe; Contract Sum: N34.86bn; Current Completion Level: 13.41%; 2020 SUKUK Payment: N4.0bn; Dualization, Bridgeworks & Drainage works; Kms Covered (2020): 23.0km
- DUALIZATION OF OBAJANA JUNCTION TO BENIN: (SECTION IV – EHOR TO BENIN) – Contractor: RCC Nigeria Ltd; Contract Sum: N35.25bn; Current Completion Level: 39.68%; 2020 SUKUK Payment: N3.5bn; Dualization & Drainage works; Kms Covered (2020): 9.0km
- RECONSTRUCTION OF ENUGU-PORT HARCOURT ROAD: (SECTION IV – ABA-PORT HARCOURT EXPWY) – Contractor: CCECC Nigeria Ltd; Contract Sum: N40.35bn; Current Completion Level: 23.74%; 2020 SUKUK Payment: N3.0bn; Expansion from four to eight lanes; Kms Covered (2020): 3.48km
- DUALIZATION OF YENEGWE-KOLO-OTUOKE-BAYELSA PALM ROAD – Contractor: CCECC Nigeria Ltd; Contract Sum: N26.49bn; Current Completion Level: 20.50%; 2020 SUKUK Payment: N2.0bn; Ongoing Dualization; Kms Covered (2020): 3.50km
- CONSTRUCTION OF IKOM BRIDGE IN CROSS RIVER STATE – Contractor: Setraco Nigeria Ltd; Contract Sum: N8.91bn; Current Completion Level: 45.02%; 2020 SUKUK Payment: N2.0bn Bridgeworks; Kms Covered (2020): 1.20km
- RECONSTRUCTION OF ODUKPANI-ITU-IKOT EKPENE ROAD IN CROSS RIVER STATE: (SECTION I – ODUKPANI-ITU BRIDGE) – Contractor: Julius Berger; Contract Sum: N54.17bn; Current Completion Level: 1.82%; 2020 SUKUK Payment: N3.0bn; Dual Carriageway works; Kms Covered (2020): 4.0km
- DUALIZATION OF SAPELE-EWU ROAD: (SECTION I – SAPELE-AGBOR IN DELTA STATE) – Contractor: CGC Nigeria Ltd; Contract Sum: N64.87bn; Current Completion Level: 8.80%; 2020 SUKUK Payment: N1.5bn; Dual Carriageway works; Kms Covered (2020): 3.0km
- DUALIZATION OF SAPELE-EWU ROAD: (SECTION II – AGBOR-EWU IN DELTA STATE) Contractor: Setraco Nigeria Ltd; Contract Sum: N47.94bn; Current Completion Level: 13.98%; 2020 SUKUK Payment: N1.5bn; Dual Carriageway works; Kms Covered (2020): 7.73km
- RECONSTRUCTION OF ALESI-UGEP ROAD: (IYAMOYUNG-UGEP) SECTION IN CROSS RIVER STATE – Contractor: Sermatech Nigeria Ltd; Contract Sum: N11.22bn; Current Completion Level: 91.0%; 2020 SUKUK Payment: N1.5bn; Carriageway works; Kms Covered (2020): 10.0km
Compiled by;
Ifunanya Ikueze